After identifying the cause of foundation failure, do what you can to prevent
  its recurrence. If there was an insect infestation, for example, treat it as
  described in section 8; if excessive surface water, put in downspouts, drainage, and so on. Then, working from the design your engineer provides, repair failed
  sections. But first you’ll have to sup port the structure above, which requires
  shoring or jacking.  Although they employ many of the same principles and materials—notably,
      big timber—shoring and jacking have different purposes. Shoring timbers
      temporarily sup port the structure as it's , or prevent sagging when the
      structure is altered. Jacking, on the other hand, lifts the structure to
      its original position or temporarily raises a section to make some task
      easier—say, raising a girder just a bit so that you can fit a full-sized
      post beneath without having to beat it into place. 
    Thus you might need only shoring to add a girder beneath a floor that's merely springy; but you should jack that floor to level if it has sagged
      appreciably, say ½-in. Use shoring to support joists while you create a
      rough opening in a floor or add a doorway to a bearing wall. But you’ll
      have to jack when a pad or post has failed, when the perimeter foundation
      has sunk, when earlier plumbers or electricians cut so much of a joist
      that it split, and so on. 
     Materials and Tools 
    When used as a temporary partition, shoring can be fabricated from 2 x
      4s; in foundation work, 4 x 4s are more commonly used for shoring studs and plates, with 4 x 8s or 4 x 10s on-edge used as carrying beams. To fully
      support loads above, studs are cut nearly to length, plumbed, and fit tightly
      to plates by driving cedar shims in with a hand sledge. Jacking also uses
      4 x 4s or 6 x 6s as posts, and as cribbing beneath the jack, which provides
      a level platform from which to jack and distributes loads over a broader
      area. 
    There are a variety of jack types to choose from. Screw jacks, perhaps
      the oldest type, vary from 12 to 20 in. high in repose and extend another
      9 to 15 in. Never raise the threaded shaft more than three-fourths its
      total length; it will be unstable beyond that. Hydraulic jacks are the
      work horses of foundation work and are rated according to the loads they
      bear: 16 to 20 tons is typical. In general, hydraulics are easier to operate and fit in tighter spaces than screw jacks; but because they lower by releasing
      hydraulic pres sure, you can’t lower them as slowly as screw types. Adjust
      able columns feature a screw mechanism atop a sleeved column, and a plate
      or bracket atop which attaches to the wooden member being raised. These
      lightweight columns, which bolster girders or joists, are intended to be
      permanent posts and are not rated as jacking devices. Lumber can also be
      used as a jack of sorts if your jacking is minimal, say, in.; cut posts
      oversized by that amount and beat them into place. 
      
Figure 10.4 Left, a hydraulic jack atop cribbing; right, a screw jack
        atop a concrete pier block.  
     Jacking Safely 
    Jacking houses is scary and should be: there are tremendous loads involved.
      But it can be done safely if you proceed slowly and observe the following
      precautions: 
    1. Wear a hard hat. Get a tetanus shot. Set up adequate light. Always
      have help within shouting distance. 
    2. Have a professional engineer assess the foundation’s failing, design
      an appropriate remedy, and recommend jack sizes and placement. 
    3. Supplement that advice with a thorough inspection of your own. Know
      what’s above: where bearing walls are, what heavy items put additional
      stress on joists, what pipes or ductwork might interfere with shoring or
      jacks, and so on. 
    4. Think things through. How much digging is there, who’s going to do
      it, where are you going to put the dirt? What machines can you rent? If
      you need more than 1 cu yd of concrete and will have it delivered, do you
      need a pumper truck? Where will you store materials? What hap pens if it
      rains? 
    5. Important: Never jack more than you must, and raise all jacks in equal
      increments—say, in. at a time. 
    6. If repairs are extensive, raise an entire wall at a time; repairing
      shorter sections wastes too much time setting and moving jacks. 
    7. Jacks and posts must be footed adequately: 
    a. Pads or cribbing must be wide enough to bear the load. Putting posts
      or jacks directly on earth is a waste of time, and precast concrete pier
      blocks right on the ground aren’t much better. Instead, put 8-in, pier
      blocks atop 2 ft x 2 ft concrete pads at least 6 in. thick. Or avoid the
      hassle of concrete altogether and use cribbing. 
    Cribbing must also be substantial.—ideally, 4 x 4s or 6 x 6s stacked so
      that they taper up from a base of 3 or 4 ft square to a top about 1 ft
      square, as in Figure 10.5A. Some builders also place a piece of 1k-in.
      plywood atop the cribbing, for an even more stable platform from which
      to jack. (Aside: When using screw or hydraulic jacks, whose heads are relatively
      small, place a-in, steel plate atop those heads so that they don’t sink
      into the wood being jacked.) 
    b. Never jack a post that's not plumb, and never jack from a base that's not level. The logic of this should be self-evident: When loads are
      transmitted straight down, there is less danger of jacks or posts kicking
      out and injuring someone. 
    Accordingly, cut the ends of all posts perfectly square, plumb posts when
      you set them, and check them for plumb periodically as the job progresses.
      If jacking posts are longer than 5 or 6 ft, brace their tops with 1-in,
      boards run diagonally. 
    Where it’s necessary to build a platform of cribbing on sloping ground,
      add an extra crib on the low side, as shown in Figure 10.5C. To hold cribbing
      on a slope, nail the crib to foundation stakes, using duplex nails for
      easy removal. 
    c. Don’t put jacking platforms too close to the edge of an excavation,
      for the soil could cave in when the jack is loaded. The rule of thumb is
      to go back 1 ft for each 1 ft you dig down. Also, don’t put jacks where
      they’ll be undermined later: if, for example, you need a needle beam to
      support joists parallel to the foundation, excavate on either side of the
      foundation and place the jacking platforms in those holes. In that manner,
      you can remove the foundation without undercutting the jacking platform. 
      
Figure 10.5 Jacks and posts must be footed adequately. (A) A safe
        setup for the cribbing can't be undermined and will not have to be moved
        later. (B) Unsafe! Here the jack is too close to the edge of a hole.
        When the jack is loaded, it could easily collapse the dirt shoulder.
        (C) Where you must jack on a slight in cline, hold cribbing in place
        with foundation stakes—or dig into the ground to create a level shelf
        from which to jack.  
     Placing the Jacks 
    Ideally, place jacks directly under the area to be jacked. This is usually
      possible when raising a sagged girder or when adding a new one. If you’re
      putting in new posts, jack up in the intervening spaces between old posts.
      Jacks every 8 ft should be sufficient under joints of a laminated girder and under girder ends not supported by the foundation wall. 
    Frequently, though, it’s not possible to place jacks directly underneath
      (e.g., when replacing a foundation). In that event you’ll need to pick
      up the load above with a beam. Where joists run perpendicular to the foundation,
      place a 4 x 8 or 4 x 10 beam on-edge under the house, within 2 ft of the
      foundation. This distance should be close enough to the end of the joists
      so that they won’t deflect, yet far enough back to give you room to work.
      A jack every 6 ft under the beam should suffice. 
    When replacing a foundation whose joists run parallel to the foundation,
      rip off siding up to the underside of the joist platform—and insert needle
      beams every 6 ft, running perpendicular to the wall, as in Figure 10.6B.
      Thus you’ll need two stands of jacks to support the needle beams: one stand
      under the house, as above, and a second stand, roughly 2 ft from the foundation,
      outside. To keep the rim (outer) joist from deflecting under the load,
      nail a second rim joist to it, and add blocking from those doubled joists
      to the first adjacent joist. Use 16d nails to end-nail blocking, and 10d
      nails to face-nail rim joists. 
      
Figure 10.6: Supporting the structure. (A) When joists run perpendicular
        to the wall you want to work on, support their load with a beam parallel
        to the wall. Allowing yourself room to work, put this beam as close to
        the wall as possible; it should be no further than 2 ft. Place jacks
        at least every 6 ft beneath the beam. (B) Where joists run parallel to
        the wall, run your beam (here called a “needle beam”) perpendicular to
        the wall as shown. To prevent its deflection under pressure, double the
        outer joist and run blocking to the next joist in. Again, place jacks
    as close to the wall as possible, and no further than 2 ft.
  |