AMAZON multi-meters discounts AMAZON oscilloscope discounts Computerization of any management function has become possible and in some cases relatively common. Computerization has yielded significant benefits, but it has also yielded disasters. Thus, if we are to be successful in computerizing maintenance management, it’s necessary to know the components of the function. The components described here are appropriate for the various types or levels of maintenance work including routine, preventive, corrective, shutdown, facility, etc.
Work Order. A document that instructs the maintenance person in what is to be done. It identifies crafts, if appropriate; materials; special tools; critical times; and provides other necessary information to accomplish the job. If complete information is n’t provided, the document is a work request. Prioritizing. The act of determining which jobs have precedence. Since the function of maintenance has limited resources available at any given time, this act is always performed in a formal or informal manner. Material Availability. A majority of the jobs performed by maintenance involve the use of materials. The material may range from a simple fastener to a sophisticated microprocessor and is necessary to provide the service that's requested. Work Plan. The asking of why, what, who, where, when, and how the maintenance group will respond to a work request. It provides logical answers to these questions.
Job Sequence. Frequently called scheduling. It recognizes priorities and resource availability and can be done at several levels. Backlog. A listing of work that's yet to be done. Control Reports. An after-the-fact record, or accounting, or what has been done and some form of measurement. Computerization inherently means organization. In the case of maintenance management it means an organized database. The components of the maintenance management function determine what the elements of the database are and include: Assignment of Costs. This usually follows the patterns established by accounting procedures used at a particular facility. It generally recognizes cost centers, departments, divisions, etc., and frequently, but not necessarily, is geographically oriented. Although a variety of approaches can be used to develop sort levels or to accumulate costs, a clear definition of the approach is critical at the start of a program to computerize maintenance management. Equipment Identification. This normally takes the form of equipment numbering and includes physical assets or functions on which maintenance resources will be expended. Careful consideration should be given here as to how finely equipment should be identified. For example, should each door in a facility be numbered or should all doors of a certain type be grouped together as one equipment? A case can be made for both approaches depending upon the type of facility and its needs. Employee Lists. Those people who will be charging time to maintenance work have to be identified. In many cases this will involve the development of a trades or crafts list. In the case of multi craft facilities it may include the several levels within the maintenance multicraft category. Trades or crafts are then associated with employee lists for time and cost analysis. Employee lists should be reconcilable to payroll but not necessarily generate or drive payroll. Priorities. The type of priority approach must be agreed upon when building the database for a computerized maintenance management system. Work Orders. The format for the work order must be agreed upon at the beginning of the computerization process. It’s the key to accumulating and distributing cost, plus developing histories for future analysis. Although no database is preloaded, one is rapidly generated. Parts Lists. In a complete maintenance planning and management control system, materials play an important role. Thus, a parts list or catalog for stocked material is necessary. These should be numbered, categorized, quantified, located, and priced when loading the database. In addition, pro visions should be made for purchased parts that are n’t stocked. Depending on the sophistication and needs of the system, several other items are recommended when loading the database. Cause Codes. Standardized identification of the basic causes of the work generated. This may be the basis for preventive maintenance programs or schedules that are part of the system. Cause codes provide a means for analyzing work and developing a corrective maintenance program. Action Codes. Standardized identifications of what was done to respond to a work request. This is basically used to identify what level of "fix" was done and again can initiate a corrective maintenance program. It should be noted here that a computerized maintenance management program does n’t, by itself, truly plan maintenance work. It can't :
In short, a computerized maintenance management program can't ask the six questions of: Why? What? Who? Where? When? How? It is, however, a fine and powerful tool for assisting in maintenance planning. A well-conceived computerized maintenance management system should provide manpower backlogs, equipment histories, equipment parts lists; determine material availability; provide preventive maintenance schedules; and track costs. WHY COMPUTERIZE MAINTENANCE MANAGEMENT? It has become commonly accepted that maintenance represents a significant portion of the cost of doing business or providing a service. The portion of cost that maintenance represents will continue to increase as the various forms of automation increase. It therefore behooves us to make optimum use of that resource called maintenance. Planning and scheduling of maintenance is one of the ways of optimizing the use of this resource. Normally, however, one of the problems is the amount of clerical work, or "paper shuffling," associated with such planning and scheduling. Computerization, if properly conceived, can minimize this problem. Computerization can provide backlog information for various types of work; availability of materials; costs by job, facility, or type of work, etc., easily. It can increase effectiveness of planning, scheduling, and cost tracking by as much as 50 percent. In addition, it can frequently provide types of information not normally available, at no additional cost. ORGANIZING FOR COMPUTERIZATION This first step in computerization of maintenance management is program definition. This is necessary whether buying a software package in the marketplace or developing programs in-house. The question of what you want done is paramount. The ability to track costs is an obvious requirement. What costs? The computerized program should give information on material availability. What information? Location? Quantity on hand? Vendor? Should the program generate purchase orders and when? What type of equipment histories should be generated? Is the program to be maintenance management oriented? Should the program provide information to corporate headquarters and between other facilities within the corporate structure? These and many other questions must be addressed in order to define the program. Normally the definition can't be achieved by the plant engineer, maintenance manager, or any other single individual. In addition, it’s not normally practical for a single individual to implement a computerized maintenance management program. An interdisciplinary team provides the most workable approach for defining the program and implementing it. Heading up or coordinating such a group should be a high-level person responsible for the maintenance function. Disciplines represented on the project team include maintenance, data processing, and accounting. Other disciplines that are frequently helpful are industrial engineering, purchasing or material control, payroll, and production. The use of the latter depends upon the personality of a particular organization. The team should be kept to a workable size, three to six people. After establishing a project team and developing the program definition, technical evaluation takes place. Answers to questions in the technical evaluation may modify program definition, but the definition must be made first. Technical evaluations include hardware evaluation and make-or-buy software considerations. IMPLEMENTATION OF A COMPUTERIZED MAINTENANCE MANAGEMENT PROGRAM Organizing for implementation of a computerized maintenance management program is one of the jobs of the project team. At this time of implementation, definitions of the following items should have been made:
Orientation of the various people concerned with the new computerized maintenance management program is the next step after organization. This may take place as part of organizing. Orientation will be necessary from the highest levels of the facilities organization to the lowest and includes production and staff as well as maintenance people. The details of the orientation appropriate for the various groups is of course different. It’s also appropriate to have concise progress review sessions as the implementation takes place. Orientation and training are similar, but there is a difference. Orientation is informing people what is going to be done or what is being done, while training is instructing people in how to do something. Training of people is a critical aspect of the implementation of a computerized maintenance management program. Training minimally should include:
In summary, although computerizing maintenance management is a demanding task, the benefits are normally significant: Better labor utilization 5 to 25 percent Equipment utilization 1 to 5 percent Stores inventory reduction 10 to 20 percent OPERATING CHARACTERISTICS OF A GOOD, FUNCTIONAL SYSTEM On-Line Inquiry. A typical complaint made about computerized systems means that they must generate too much paper. Thus one of the prime characteristics of a good computerized maintenance management system means that it has on-line inquiry and provides screen viewing for the areas of work orders, material, and equipment. Work Orders. The work order is the controlling document in any maintenance management control program. When viewing a work order on a screen in a computerized program, the following information should be readily available:
Other information may be desired but the foregoing are necessary for good maintenance management. In addition, the program should be able to selectively bring up work orders for observation. The selection criteria should include:
Through the use of any one or combination of the above selection criteria, file search time by the viewer is greatly reduced. Material. A good storeroom is helpful in optimum equipment and manpower utilization. Screen viewing of material in that stockroom should include:
Equipment. The third leg of a good maintenance management program concerns equipment. Screen viewing for this section should include:
Custom Report Generation. A second characteristic of a good computerized maintenance management system is the ability to generate specific reports on demand. The selection criteria should be similar to those for screen viewing and include the following reports: Work Orders
Performance Reports. The third characteristic that a good system should have is measured performance against some type of target or budget. These reports should be brief yet meaningful for maintenance management and include:
The most important characteristic is that the program is "user-friendly." I.e., users needing information can get it easily, usually by means of a series of menus and questions asked by the computer. Teaching the user to respond to menus and questions is easier than teaching the user how to query the computer in its own language. WORK ORDER SYSTEM Purpose. A formal work order system provides an information network incorporating inputs and outputs for all the various phases of the maintenance program. Scope. The work order system and its procedures provide a uniform means of information flow for requesting, planning, scheduling, controlling, recording, and analyzing the performance of all the work done by the maintenance department. The work order form serves as the vehicle for communicating information related to specific work requested of maintenance. More specifically, the work order system provides:
All too often verbal work orders result in performance of unimportant, unauthorized, unnecessary, and even unwanted work. To reduce the possibility of this happening, it’s essential that all requests for maintenance services be submitted in writing on the work order form. Requests for ser vice may be initiated by maintenance or production personnel desiring to have work performed. The work order is the basic authorization for performance of maintenance work and , together with the "planning package," will produce an accurate account of individual maintenance jobs. It may be used as a reference for similar jobs in the future. R-I-M-E (Ranking Index for Maintenance Expenditures) PRIORITY SYSTEM Purpose. In general, it can be said that there is never enough time, money, or manpower to perform all of the maintenance work that's needed and /or desired. The decision as to what maintenance work is performed and when, if not systematized, will be made on the subjective judgment of any one or a combination of several persons. If the intent, as it generally is, is to perform the most badly needed and important work first, then it’s desirable to have a reasonably objective system to identify priorities for maintenance work that can serve as a guide for the maintenance department. The intent, therefore, is to develop a relative priority ranking system for maintenance work based on the collective judgment of those responsible for the operation of the facility. The best method of achieving this is one which produces a quantitative index of the relative importance of a job at the time that the need for the job occurs. Thus personal judgments are less likely to influence the resultant ranking of jobs by priority. Scope. The system for establishing priority values is called RIME (Ranking Index for Maintenance Expenditures). This system, which provides a wide range of priority numbers, will best provide a true ranking of all the varied jobs which maintenance must perform. To establish a sound priority system, the following three elements are essential. Without them, the system will function improperly. 1. The priority system must encompass everything within the plant. 2. All production and maintenance personnel involved must understand and respect the priority system. 3. The priority system must be based on profit. The computing of job priority indexes considers the equipment and facilities (equipment code) in conjunction with the importance of the work (work class). These two considerations provide multiples which establish the value of the work requested. The higher this value, the more important the request. PLANNING PROCEDURE DEFINED The following outline describes the procedure for work order planning in detail. 1 Decision has been made that the work order requires planning. 2 Analyze the work requested: a. Is the information complete and adequate? b. Is the work needed? c. Why is the work needed? d. Can anything be done to avoid recurrence in the future? e. Visit the job site, if appropriate. 3 Determine the basic approach to be followed: a. What is the priority of the work? b. What effect will it have on operating? c. What are the future plans for the equipment? d. Is the equipment scheduled to be overhauled, replaced, or phased out? e. Can repair provide the same reliability as a replacement at a lower cost? f. Make sketches as required. 4 Identify special considerations, needs, and conditions: Is production assistance required? 5 Identify need for engineering: a. If required, notify engineering or have the appropriate person do so. b. If maintenance is involved, identify work for maintenance. 6 Identify need for contract service: If required, contact contractor or have the appropriate person do so. 7 Is maintenance involved? If maintenance is involved, coordinate job. 8 Identify work for the maintenance department. 9 Identify information needed. 10 Identify instructions required: If description of work does n’t clearly state what work is to be done, provide instructions. 11 Identify manpower required. 12 Estimate man-hours required. 13 Identify any special tools or permits required: a. Is work overhead? b. If welding is required, is a welding permit needed? c. List any special tools. 14 Identify material/parts required: Are any special materials/parts needed? If so, list them. 15 Determine if materials/parts are stock items; if so, list location. 16 If materials/parts are nonstock or out-of-stock items: a. Order. b. Record the work order number on the purchase order and the purchase-order number on the work order. c. Change the status of the work order to delayed materials in the backlog file. 17 Material/parts received: a. As the material/parts are received they are charged to the work order. b. When all the parts are received, the work order status is changed from pending material/parts in the backlog file. 18 All material/parts and tools are staged. 19 Identify the supervisor that will be responsible for the work. 20 The work order is now planned. 21 Backlog file: Planned work order's status is changed to the appropriate ready-to-run category, and it’s placed into the backlog file. 22 Planned work orders are scheduled: The work order is pulled from the backlog file and given to the supervisor with the weekly schedule. Flowchart showing how the maintenance procedure moves along in logical sequential stages. PLANNING FOLLOW-UP Effective planning requires observing preplanned job progress to eliminate potential delays or problems that may arise. The planner should occasionally observe planned work in progress with the intention of improving his preplanning expertise. During the follow-up process, the planner may address problem areas which are common to planning functions. These areas are:
ANALYSES and DISPLAYS Work Orders The work order section contains information pertaining to specific work for a piece of equipment or facility. This work could be corrective or preventive maintenance, emergency, routine, or standing orders. The data collected provide answers to the standard questions of what, when, where, why, who, how much, and how often. Output from the system consists of two types of reporting. 1. Planning function data and specific information about job orders are provided on request by the following reports:
Backlog and completed job reports can be created based on a multitude of selection criteria, including:
2. The second type of output data provides management with performance control data on a weekly and monthly basis through the following listed reports.
The control reports provide summaries by operating organization and maintenance craft. Work Order Module Examples of the following selected screens and reports are included. Screens
Reports. The following informational reports can be generated using the report data selection screens. _ Work order status report
Parts Inventory The parts inventory section provides control over the second key element in an effective maintenance system, the first key element being what has to be done, i.e., work orders. The primary functions of the inventory system are:
Examples of the following selected screens and reports are included. Screens
Equipment The equipment section contains data used to identify individual pieces of equipment or physical locations and to track history on labor and material costs. The accumulation of data retained in the system provides the means for:
Examples of the following selected screens and reports are included. Screens
Reports